Western Transmission (Gujarat) Limited had implemented the laying of 477 km 400 kV double circuit transmission line as part of the Western Region System Strengthening Scheme Project C in the State of Gujarat and Madhya Pradesh subject to the terms and conditions of the implementation agreement dated 23rd November, 2007.
The Project consists of the following transmission lines with a total transmission line length of 487km, constructed in the following 3 sections:
All the three lines have been commissioned, achieved commercial operation and are currently operational.
The commercial operation (“COD”) of the lines were achieved as follows:
The lines have been constructed on Build, Own and Operate basis for a period of 25 years. The Issuer has always maintained surpassed the normative availability of 98%.